Kazan Power Plant 1

Turnkey construction of 50 MW Gas turbine plant
Location:
Russia, Kazan
Realization time:
2003-2005 гг.

Types of jobs:

  • Design documentation development
  • Dismantling of the existing production facilities
  • Supply and installation of:
  • Gas turbine units
  • Heat recovery steam generators
  • Power generators
  • Compressor stations
  • Stack construction
  • Development and implementation of automation process control system
  • Commissioning and start-up works

Services
  • Design
  • Reconstruction
  • Supply
  • Installation
  • Adjustment works
Other works performed
Do you need to
implement a similar project?
Connect to us