Substation Osinovo

Reconstruction of substation
Location:
Russia, Kazan
Realization time:
2005-2006

Types of jobs:

  • Construction of indoor switchgear-10 kV of the substation "Osinovo" combined with the operational control station with the installation of the cells To-63 in the amount of 32 pieces
  • Reconstruction of relay protection devices with the replacement of protection on microprocessor
  • Reconstruction of the construction part of the substation with the reconstruction of oil-receiving devices and reinforced concrete fencing of the substation territory.
  • Replacement of power transformers TMN-16000/110 on TRDN-25000/100 with a split winding and installed additional input cells 10 kV.

The purpose of the reconstruction is to increase the power from 12,500 kW to 29,150 kW.

Services
  • Construction
  • Reconstruction
Other works performed
Do you need to
implement a similar project?
Connect to us